|
It
includes 11kV vacuum switchgear from Holec (another Eaton Electric
company) and MEM low voltage switchboards and panelboards. Some
products, such as the 18 cast resin transformers, have been sourced
from outside the MEM group.
The
building is supplied by nine packaged substations, installed
at different levels - one in the basement, six at level 15 and
two at level 42. Four of these provide landlord's services and
five supply tenants' services.
The
substations have been designed specially for the project by MEM.
Incoming 11kV supplies are controlled by 600A Holec lnnovac SVS
vacuum circuit-breakers. The substations are double-ended, with
a 3.5MVA 11kV/41 5V cast resin transformer at each end. Force
cooling can increase the transformer rating to 4.5MVA.
Each
transformer feeds a 6300A busbar system via two manually-operated
6300A MEM air circuit-breakers, divided by a third ACB bus-section
switch. Outgoing feeders are air circuit-breakers ranging from
400A to 5,000A. To meet the space constraints of the project,
MEM designed a special cubicle which would allow three air circuit-breakers
to be stacked vertically.
The
transformers and their enclosures were delivered to site separately.
The enclosures were delivered in "flat-pack" form,
with the front, back, sides and base packed in wooden crates.
The top section, with busbars, was pre-fabricated at MEM's Premier
Street factory, in Birmingham.
Essential
services design is critical to a building of this nature. MEM
has designed and supplied three main essential services switchboards
and 17 essential services panelboards for the building. In the
event of loss of mains supply, standby generators feed the three
switchboards. The essential services panelboards are normally
fed from the packaged substations, via automatic transfer switches;
in an emergency these transfer the load to the standby generators
via the essential services switchboards.
The
switchboards and panelboards are Memform and Memform SD units
incorporating a combination of outgoing Memshield 2 MCCBs and
combination fuse switches. Incoming devices range from ACBs to
switch disconnectors.
MEM
is also supplying eight special switchboards for tenants' supplies.
Meanwhile,
in the neighbouring building at 8-16 Canada Square, the company
is completing one of the largest busbar trunking orders ever
placed in Europe. When completed, the two new towers, both 42
storeys and 200m (660ft) high, will be the tallest buildings
in Canary Wharf, after the 50-storey, 244m (800ft) Canary Wharf
tower at One Canada Square. The two new towers are being built
by Canary Wharf Contractors Ltd. and will be leased to major
International banks. |